Joining the Renewable Heating Hub forums is completely free and only takes a minute. By registering you’ll be able to ask questions, join discussions, follow topics you’re interested in, bookmark useful threads and receive notifications when someone replies. Non-registered members also do not have access to our AI features. When choosing your username, please note that it cannot be changed later, so we recommend avoiding brand or product names. Before registering, please take a moment to read the Forum Rules & Terms of Use so we can keep the community helpful, respectful and informative for everyone. Thanks for joining!
ASHP install contract and BUS grant money
Hello! I today received my first quote from an installer who actually came to the house (two others so far were preliminary online-only guess-quotes). I was a little surprised to see one thing in the contract: it states that I have the pay the £7500 extra if the BUS grant does not go through.
Is that a typical way that installers deal with the BUS grant in contracts?
My first thought was: they are MCS certified, so they know what is required to be done with the actual install and the paperwork ... I have no ability myself to influence if the BUS grant succeeds, so why am I on the hook for the cost (lack of rebate) if Ofgem does not pay out?
I searched on this forum and found @grahamh Graham's post about BUS ( https://renewableheatinghub.co.uk/forums/renewable-heating-air-source-heap-pumps-ashps/the-new-heat-pump-grant-bus ) and he did mention something that made me have a second thought -- to quote him:
They will quote and then register the quote with the BUS website. Ofgem who run the BUS scheme will contact the homeowner to check they have been quoted and are happy, if they are the installer will be told to proceed and a voucher will be put aside for the job. Once the job is installed the installer will invoice the homeowner the cost of the heat pump minus £5000. The homeowner will be asked to confirm to Ofgem that they are happy. When they confirm they are the voucher will be issued to the installer, they will or should receive the £5000 within a week from Ofgem.
(He wrote this before it went up to £7500)
Is the installer just trying to cover himself if I do NOT confirm to Ofgem that "I'm Happy" with the installation? That part I guess I do control.
Sounds to me like a bit of rear-end covering tactics; should things go pear shaped for any reason, you are on the hook for the ‘Bus Ticket’ element. This may be a component in their standard contract terms, but if so, it suggests that they may not have sufficient confidence in their own workmanship! Are you otherwise happy with the installer? What is your gut feeling telling you? Regards, Toodles.
Toodles, heats his home with cold draughts and cooks food with magnets.
Posted by: @sussex-greenishHello! I today received my first quote from an installer who actually came to the house (two others so far were preliminary online-only guess-quotes). I was a little surprised to see one thing in the contract: it states that I have the pay the £7500 extra if the BUS grant does not go through.
Mine did that also, I wouldn't be surprised if its common/written into the MCS contract template.
You get about 3 emails from the BUS people either asking you to confirm the installer or confirming that the grant has been provisionally authorised, so in practice there is a reasonable degree of reassurance. In particular there is a point in the process (before the installation) where the installer has made the application for the grant and you have to confirm that you authorise the installer to access the grant on your behalf. Until this point I wouldn't regard it as secure, so no way would I let an installer go ahead until this point was reached.
4kW peak of solar PV since 2011; EV and a 1930s house which has been partially renovated to improve its efficiency. 7kW Vaillant heat pump.
-
High air source heat pump running costs – Vaillant AroTherm Plus
1 month ago
-
Bosch CS5800i 7kW replacing Greenstar Junior 28i
2 months ago
-
Rodents! A word of warning for heat pump owners
4 months ago
-
Ecodan Pump Issues… Circulation pump turns off when heat pump compressor turns off
5 months ago
-
Running my new Nibe ASHP efficiently
5 months ago
- 26 Forums
- 2,658 Topics
- 62.2 K Posts
- 301 Online
- 7,060 Members
Join Us!
Directory
Latest Posts
-
Heat Pump Replacement by Cinergy
I would rate the installation process by Cinergy as exc...
By trebor12345 , 3 minutes ago
-
RE: Indevolt Batteries UK Support & Info Thread
That's almost correct, but not quite. The Indevolt st...
By Transparent , 7 minutes ago
-
RE: Cooling with air to water heat pumps
On the two huge (10m² each) south facing windows I inst...
By bobflux , 2 hours ago
-
RE: GivEnergy inverter tripping due to over-voltage?
@transparent I don't think Axle have any involvement...
By Tim441 , 2 hours ago
-
I'm the general case no (at least not yet). But if ins...
By JamesPa , 3 hours ago
-
RE: Failed Heat Pump Install: IWA Claim Rejected
Many of the estimates we received mention IWA and RECC....
By Batpred , 1 day ago
-
RE: Rural burning – I've had enough
Same here in Finland. It's strictly forbidden ...
By upnorthandpersonal , 1 day ago
-
RE: Renewables & Heat Pumps in the News
Something worth flagging... we've just published a news...
By Mars , 1 day ago
-
RE: Renewable Heating Hub Homeowners' Q&A Podcast
The Homeowners' Q&A podcast is back... I've changed...
By Mars , 1 day ago
-
RE: Anyone concerned about GivEnergy?
I have already signed up with Axle so yes, that takes c...
By KevH , 1 day ago
-
@batpred Would it pass the airbnb feedback test no. I...
By EtchedPixels , 2 days ago
-
A quick update... we've just launched the beta version ...
By Mars , 2 days ago
-
RE: Who Actually Owns a Heat Pump in Britain? We Asked. Here Is What We Found.
The age part doesn't surprise me - only 25% of UK home ...
By EtchedPixels , 2 days ago