I received the BUS Grant permission email yesterday evening, which I've returned confirming my consent to the process, so we're definitely moving from the theory part of the exercise to the execution now.
We've already started the task of clearing some space in the more problematic parts of the house to enable the relevant access for the installation. The old airing cupboard is no longer a dumping ground for suitcases, towels, etc and can now house a cylinder once again. The loft has had something of a clear-out, with items being relocated to the tip or charity shop and we've dismantled a huge self-built desk that the previous owner had left us in an upstairs bedroom, which has been useful in it's time, but takes up far more of the room than it needs to. We'll replace it with a smaller one after the installation, but the radiator in that room, which was the most challenging one for the surveyors to get access to for measurement, is now fully accessible.
We're weeks away from an installation, but its quite a relief to get these jobs out of the way at an early stage. Everything else will be relatively minor in comparison, but can only really be done close to the time as their in rooms which are in constant use.
130m2 4 bed detached house in West Yorkshire
10kW Mitsubishi Ecodan R290 Heat Pump - Installed June 2025
6.3kWp PV, 5kW Sunsynk Inverter, 3 x 5.3kWh Sunsynk Batteries
MyEnergi Zappi Charger for 1 EV (Ioniq5) and 1 PHEV (Outlander)
User of Havenwise (Full control Jun-Dec 2025, DHW only from early Dec)
Subscriber to MelPump App data via CN105 Dongle Kit
Just to briefly update things, we now have a confirmed installation date starting on 24th June, so things have moved rapidly from theoretical to 'this is happening'.
I'm somewhat sceptical that they're going to achieve the target of a 2-day installation (albeit 'very long days') but we'll see. There won't be a huge issue if it ultimately runs over, but the target that they've set for themselves seems ambitious.
We've already cleared out some of the more problematic areas for access, including emptying the airing cupboard which had been a useful storage cupboard since the old hat water cylinder was removed from there in 2014 when the combi boiler was installed.
I'll try to document the installation process as best as possible within this thread. It's quite exciting to think that this is actually going to happen now!
130m2 4 bed detached house in West Yorkshire
10kW Mitsubishi Ecodan R290 Heat Pump - Installed June 2025
6.3kWp PV, 5kW Sunsynk Inverter, 3 x 5.3kWh Sunsynk Batteries
MyEnergi Zappi Charger for 1 EV (Ioniq5) and 1 PHEV (Outlander)
User of Havenwise (Full control Jun-Dec 2025, DHW only from early Dec)
Subscriber to MelPump App data via CN105 Dongle Kit
@sheriff-fatman Good luck!
2 days is definitely short, curious how big the installation team will be.
CEO and co-founder at HavenWise
@hcas Perhaps the installers are those miniature Chinese robots - you could get quite a few of those in the average dwelling at the same time! Toodles.
Toodles, heats his home with cold draughts and cooks food with magnets.
@sheriff-fatman good luck, and yes, please document your journey here.
Two days is extremely optimistic unless they have a really big team.
Get a copy of The Ultimate Guide to Heat Pumps
Subscribe and follow our YouTube channel!
@editor I'm not expecting a sizeable team, hence the scepticism at their timescales.
130m2 4 bed detached house in West Yorkshire
10kW Mitsubishi Ecodan R290 Heat Pump - Installed June 2025
6.3kWp PV, 5kW Sunsynk Inverter, 3 x 5.3kWh Sunsynk Batteries
MyEnergi Zappi Charger for 1 EV (Ioniq5) and 1 PHEV (Outlander)
User of Havenwise (Full control Jun-Dec 2025, DHW only from early Dec)
Subscriber to MelPump App data via CN105 Dongle Kit
@sheriff-fatman just keep an eye on them... definitely keep us updated and add photos if you can.
Get a copy of The Ultimate Guide to Heat Pumps
Subscribe and follow our YouTube channel!
Our ASHP installation was originally scheduled for 2 days and ended up going into a third day. We had a two man team of installers (who were brilliant), plus an electrician on site for one day to connect up the electrics.
The installation involved removal of old oil boiler, replacement of 12 radiators and a complete replumb on the heating side to 22/15mm copper replacing existing plastic micro-bore pipework.. To be fair, they may just have achieved it in two days if we had not encountered some routing difficulties on the plumbing side. That said, the two guys worked 12 hour days and did not stop - they were brilliant. They did look in disbelief on the first morning doing their walk through that the job had been scheduled for two days!
Samsung 12kW gen6 ASHP with 50L volumiser and all new large radiators. 7.2kWp solar (south facing), Tesla PW3 (13.5kW)
Solar generation completely offsets ASHP usage annually. We no longer burn ~1600L of kerosene annually.
Posted by: @old_scientistOur ASHP installation was originally scheduled for 2 days and ended up going into a third day. We had a two man team of installers (who were brilliant), plus an electrician on site for one day to connect up the electrics.
The installation involved removal of old oil boiler, replacement of 12 radiators and a complete replumb on the heating side to 22/15mm copper replacing existing plastic micro-bore pipework.. To be fair, they may just have achieved it in two days if we had not encountered some routing difficulties on the plumbing side. That said, the two guys worked 12 hour days and did not stop - they were brilliant. They did look in disbelief on the first morning doing their walk through that the job had been scheduled for two days!
That's helpful, as it's essentially the same scenario as has been outlined for our installation, but we don't have replacement pipework scheduled for our own installation, as we're on 15mm copper. The two days were outlined as "very long days" and we've been told to expect the electrician on day 2, so you've at least provided a scenario where this might be feasible.
130m2 4 bed detached house in West Yorkshire
10kW Mitsubishi Ecodan R290 Heat Pump - Installed June 2025
6.3kWp PV, 5kW Sunsynk Inverter, 3 x 5.3kWh Sunsynk Batteries
MyEnergi Zappi Charger for 1 EV (Ioniq5) and 1 PHEV (Outlander)
User of Havenwise (Full control Jun-Dec 2025, DHW only from early Dec)
Subscriber to MelPump App data via CN105 Dongle Kit
@old_scientist And just to bring some ‘balance’! to this topic: Our ASHP with 8 replacement out of an existing 10 radiators plus a dual fuel towel rail and a Sunamp Thermino DHW heating system, removing an aging gas boiler and 99 litre DHW tank and decommissioning of a cold water storage tank in the loft… estimated to be 5 days work … took 3 weeks! Extenuating circs. of course, supply of components, wrong radiators sent, 3 attempts to elevate the Sunamp upstairs. Overall a good job but when installers enjoy working with all windows and external doors wide open ALL DAY LONG in January and into February, this is not a thing one forgets about.😳 Toodles.
Toodles, heats his home with cold draughts and cooks food with magnets.
Posted by: @sheriff-fatmanPosted by: @old_scientistOur ASHP installation was originally scheduled for 2 days and ended up going into a third day. We had a two man team of installers (who were brilliant), plus an electrician on site for one day to connect up the electrics.
The installation involved removal of old oil boiler, replacement of 12 radiators and a complete replumb on the heating side to 22/15mm copper replacing existing plastic micro-bore pipework.. To be fair, they may just have achieved it in two days if we had not encountered some routing difficulties on the plumbing side. That said, the two guys worked 12 hour days and did not stop - they were brilliant. They did look in disbelief on the first morning doing their walk through that the job had been scheduled for two days!
That's helpful, as it's essentially the same scenario as has been outlined for our installation, but we don't have replacement pipework scheduled for our own installation, as we're on 15mm copper. The two days were outlined as "very long days" and we've been told to expect the electrician on day 2, so you've at least provided a scenario where this might be feasible.
Yes, it's "doable" if everything goes to plan, they arrive early and all the correct kit also arrives early and you have a good hard working team of installers. Our DHW tank was sited in the space vacated by the oil combi-boiler, so all the pipework was already at that location. Not having to re-plumb the heating circuit will help - they may just need to adjust radiator tails to fit any larger radiators, but that's easy enough to do. In my mind, I'd block out the week and then be pleased if it's all done in 2-3 days. Anything longer than that, and something has gone seriously awry, but as @toodles highlights, it only takes a few supply issues and things can quickly escalate.
Our guys turned up at 8am on the first morning, and their delivery lorry arrived shortly after containing everything for the job (very well organised). They were missing a few small items which they identified and ordered on next day delivery, but nothing that really held up work. By the time they'd unloaded the lorry and we'd done a full walk through of the job (and had a pot of tea), it was probably mid morning before the tools came out. They nkew they were up against it to complete in 2 days, so they stayed to 8pm each night, and then finished by around lunchtime on the third day, before leaving to drive half way across the country to their next job.
In contrast, our neighbours had an ASHP installed around the same time, and their installers would turn up mid morning and be gone by 3:30-4pm (it was summer and the beach is nearby!). The work was sloppy and they had some big leaks. So a lot depends on getting good installers.
Samsung 12kW gen6 ASHP with 50L volumiser and all new large radiators. 7.2kWp solar (south facing), Tesla PW3 (13.5kW)
Solar generation completely offsets ASHP usage annually. We no longer burn ~1600L of kerosene annually.
Today's the start of the installation and, having spent a bit of time around the installation team, I'm feeling quite relaxed about things. They turned up at 7:30am and got their heads down. The more senior guy has been fitting heat pumps as his primary work for the last 7 years, and clearly knows what he's talking about. The main team is two guys, and we've had a labourer turn up for a period of time. They've spoken to the electrician, who's coming out tomorrow, to provide info on what's available for him to use on the fuse board. I've heard them describe it as a "nice job" so far, so they've clearly not seen anything to give them concerns. They also seem quite confident that they'll get finished within the two days, so we'll see if that's the case.
Radiators, heat pump and cylinder have all been delivered this morning (they're half expecting something to be missing/incorrect from the radiator list, which seems to be a fairly standard occurrence, but no indication of this as yet, and clearly something they're used to). I'm currently staring at a monster of a K3 that's going in the kitchen/dining area, and have watched them carry through radiators to go into the upstairs rooms.
So far so good (touch wood!) First impressions only, but I've gained a huge amount of reassurance already from having seen the guys go about their work, and from the interactions I've had with them while trying to keep out of their way.
130m2 4 bed detached house in West Yorkshire
10kW Mitsubishi Ecodan R290 Heat Pump - Installed June 2025
6.3kWp PV, 5kW Sunsynk Inverter, 3 x 5.3kWh Sunsynk Batteries
MyEnergi Zappi Charger for 1 EV (Ioniq5) and 1 PHEV (Outlander)
User of Havenwise (Full control Jun-Dec 2025, DHW only from early Dec)
Subscriber to MelPump App data via CN105 Dongle Kit
- 26 Forums
- 2,396 Topics
- 54.3 K Posts
- 310 Online
- 6,077 Members
Join Us!
Worth Watching
Latest Posts
-
RE: Considering MLCP (Multi-Layer Composite Pipe) for ASHP
OK, TBH I dont know enough about MLCP to comment with a...
By JamesPa , 3 minutes ago
-
RE: Predicted Heat Loss from MCS calcs vs EPC vs actual
My gut feeling is that the heat pump is right sized. ...
By Tim441 , 24 minutes ago
-
RE: Heat pump not reaching flow temperature
Peak Energy Products most recent accounts (to June 2024...
By JamesPa , 51 minutes ago
-
RE: Power outages and storms: A surprisingly good DNO experience
Agreed, which is no more nor less than a customer shoul...
By Majordennisbloodnok , 2 hours ago
-
RE: Running from backup generaor in powercut?
@batpred In our case, 3 times each day when the Octopus...
By Toodles , 2 hours ago
-
RE: Advice for a novice on Mitsubishi Ecodan 6kW
Hi @sheriff-fatman Cycling at 5C and below is usuall...
By RobS , 3 hours ago
-
RE: Recommended home battery inverters + regulatory matters - help requested
The diagram describes what happens inside the Solis. Al...
By Batpred , 4 hours ago
-
RE: New Fogstar 15.5kWh upright solution
@batpred Here's the latest Fogstar ready built pack....
By Bash , 4 hours ago
-
RE: RDSAP10 effect on existing heat pump EPC rating?
@mike-patrick yes, even though the current system is ru...
By Tim441 , 4 hours ago
-
RE: Solis inverters S6-EH1P: pros and cons and battery options
Solis confirmed that the S6 works with a single battery...
By Batpred , 5 hours ago
-
RE: Who has a V2G EV installation
I am wondering if in any V2X, would the car battery eve...
By Batpred , 6 hours ago
-
RE: Setback savings - fact or fiction?
Yes, by calculating it manually from the minute data, w...
By cathodeRay , 7 hours ago
-
Fan unit Making terrible noise HELP!!
One of a pair of fan units on an Earth Save Classic II ...
By GutoFfowc , 7 hours ago
-
RE: New Mitsubishi Ecodan 11.2kW installation - L9 errors and maybe more
OK. I think your system, which seems well designed, is...
By JamesPa , 9 hours ago
-
RE: Heatpunk Floor plan issues
It's usually the complete opposite... seldom that Safar...
By Mars , 22 hours ago
-
RE: Fan is clipping ice build up from the front of unit.
@majordennisbloodnok I’ll not go there thanks! Toodles.
By Toodles , 1 day ago
-
RE: Running my new Nibe ASHP efficiently
I'm new to the forum. Did you get a reply to this last ...
By Mike @ Camelot , 1 day ago
-
RE: ASHP Energy Consumption: Aira 12kW heat pump
@grantmethestrength MCS requirements for DHW capacity h...
By Toodles , 1 day ago
-
RE: Help me keep the faith with my air source heat pump installation
@adamk I'm observing my own system at low temperatures ...
By dr_dongle , 1 day ago



