I received the BUS Grant permission email yesterday evening, which I've returned confirming my consent to the process, so we're definitely moving from the theory part of the exercise to the execution now.
We've already started the task of clearing some space in the more problematic parts of the house to enable the relevant access for the installation. The old airing cupboard is no longer a dumping ground for suitcases, towels, etc and can now house a cylinder once again. The loft has had something of a clear-out, with items being relocated to the tip or charity shop and we've dismantled a huge self-built desk that the previous owner had left us in an upstairs bedroom, which has been useful in it's time, but takes up far more of the room than it needs to. We'll replace it with a smaller one after the installation, but the radiator in that room, which was the most challenging one for the surveyors to get access to for measurement, is now fully accessible.
We're weeks away from an installation, but its quite a relief to get these jobs out of the way at an early stage. Everything else will be relatively minor in comparison, but can only really be done close to the time as their in rooms which are in constant use.
Just to briefly update things, we now have a confirmed installation date starting on 24th June, so things have moved rapidly from theoretical to 'this is happening'.
I'm somewhat sceptical that they're going to achieve the target of a 2-day installation (albeit 'very long days') but we'll see. There won't be a huge issue if it ultimately runs over, but the target that they've set for themselves seems ambitious.
We've already cleared out some of the more problematic areas for access, including emptying the airing cupboard which had been a useful storage cupboard since the old hat water cylinder was removed from there in 2014 when the combi boiler was installed.
I'll try to document the installation process as best as possible within this thread. It's quite exciting to think that this is actually going to happen now!
@sheriff-fatman Good luck!
2 days is definitely short, curious how big the installation team will be.
CEO and co-founder at HavenWise
@hcas Perhaps the installers are those miniature Chinese robots - you could get quite a few of those in the average dwelling at the same time! Toodles.
Toodles, heats his home with cold draughts and cooks food with magnets.
@sheriff-fatman good luck, and yes, please document your journey here.
Two days is extremely optimistic unless they have a really big team.
Get a copy of The Ultimate Guide to Heat Pumps
Subscribe and follow our Homeowners’ Q&A heat pump podcast
@sheriff-fatman just keep an eye on them... definitely keep us updated and add photos if you can.
Get a copy of The Ultimate Guide to Heat Pumps
Subscribe and follow our Homeowners’ Q&A heat pump podcast
Our ASHP installation was originally scheduled for 2 days and ended up going into a third day. We had a two man team of installers (who were brilliant), plus an electrician on site for one day to connect up the electrics.
The installation involved removal of old oil boiler, replacement of 12 radiators and a complete replumb on the heating side to 22/15mm copper replacing existing plastic micro-bore pipework.. To be fair, they may just have achieved it in two days if we had not encountered some routing difficulties on the plumbing side. That said, the two guys worked 12 hour days and did not stop - they were brilliant. They did look in disbelief on the first morning doing their walk through that the job had been scheduled for two days!
Samsung 12kW gen6 ASHP with 50L volumiser and all new large radiators. 7.2kWp solar (south facing), Tesla PW3 (13.5kW)
Solar generation completely offsets ASHP usage annually. We no longer burn ~1600L of kerosene annually.
Posted by: @old_scientistOur ASHP installation was originally scheduled for 2 days and ended up going into a third day. We had a two man team of installers (who were brilliant), plus an electrician on site for one day to connect up the electrics.
The installation involved removal of old oil boiler, replacement of 12 radiators and a complete replumb on the heating side to 22/15mm copper replacing existing plastic micro-bore pipework.. To be fair, they may just have achieved it in two days if we had not encountered some routing difficulties on the plumbing side. That said, the two guys worked 12 hour days and did not stop - they were brilliant. They did look in disbelief on the first morning doing their walk through that the job had been scheduled for two days!
That's helpful, as it's essentially the same scenario as has been outlined for our installation, but we don't have replacement pipework scheduled for our own installation, as we're on 15mm copper. The two days were outlined as "very long days" and we've been told to expect the electrician on day 2, so you've at least provided a scenario where this might be feasible.
@old_scientist And just to bring some ‘balance’! to this topic: Our ASHP with 8 replacement out of an existing 10 radiators plus a dual fuel towel rail and a Sunamp Thermino DHW heating system, removing an aging gas boiler and 99 litre DHW tank and decommissioning of a cold water storage tank in the loft… estimated to be 5 days work … took 3 weeks! Extenuating circs. of course, supply of components, wrong radiators sent, 3 attempts to elevate the Sunamp upstairs. Overall a good job but when installers enjoy working with all windows and external doors wide open ALL DAY LONG in January and into February, this is not a thing one forgets about.😳 Toodles.
Toodles, heats his home with cold draughts and cooks food with magnets.
Posted by: @sheriff-fatmanPosted by: @old_scientistOur ASHP installation was originally scheduled for 2 days and ended up going into a third day. We had a two man team of installers (who were brilliant), plus an electrician on site for one day to connect up the electrics.
The installation involved removal of old oil boiler, replacement of 12 radiators and a complete replumb on the heating side to 22/15mm copper replacing existing plastic micro-bore pipework.. To be fair, they may just have achieved it in two days if we had not encountered some routing difficulties on the plumbing side. That said, the two guys worked 12 hour days and did not stop - they were brilliant. They did look in disbelief on the first morning doing their walk through that the job had been scheduled for two days!
That's helpful, as it's essentially the same scenario as has been outlined for our installation, but we don't have replacement pipework scheduled for our own installation, as we're on 15mm copper. The two days were outlined as "very long days" and we've been told to expect the electrician on day 2, so you've at least provided a scenario where this might be feasible.
Yes, it's "doable" if everything goes to plan, they arrive early and all the correct kit also arrives early and you have a good hard working team of installers. Our DHW tank was sited in the space vacated by the oil combi-boiler, so all the pipework was already at that location. Not having to re-plumb the heating circuit will help - they may just need to adjust radiator tails to fit any larger radiators, but that's easy enough to do. In my mind, I'd block out the week and then be pleased if it's all done in 2-3 days. Anything longer than that, and something has gone seriously awry, but as @toodles highlights, it only takes a few supply issues and things can quickly escalate.
Our guys turned up at 8am on the first morning, and their delivery lorry arrived shortly after containing everything for the job (very well organised). They were missing a few small items which they identified and ordered on next day delivery, but nothing that really held up work. By the time they'd unloaded the lorry and we'd done a full walk through of the job (and had a pot of tea), it was probably mid morning before the tools came out. They nkew they were up against it to complete in 2 days, so they stayed to 8pm each night, and then finished by around lunchtime on the third day, before leaving to drive half way across the country to their next job.
In contrast, our neighbours had an ASHP installed around the same time, and their installers would turn up mid morning and be gone by 3:30-4pm (it was summer and the beach is nearby!). The work was sloppy and they had some big leaks. So a lot depends on getting good installers.
Samsung 12kW gen6 ASHP with 50L volumiser and all new large radiators. 7.2kWp solar (south facing), Tesla PW3 (13.5kW)
Solar generation completely offsets ASHP usage annually. We no longer burn ~1600L of kerosene annually.
Today's the start of the installation and, having spent a bit of time around the installation team, I'm feeling quite relaxed about things. They turned up at 7:30am and got their heads down. The more senior guy has been fitting heat pumps as his primary work for the last 7 years, and clearly knows what he's talking about. The main team is two guys, and we've had a labourer turn up for a period of time. They've spoken to the electrician, who's coming out tomorrow, to provide info on what's available for him to use on the fuse board. I've heard them describe it as a "nice job" so far, so they've clearly not seen anything to give them concerns. They also seem quite confident that they'll get finished within the two days, so we'll see if that's the case.
Radiators, heat pump and cylinder have all been delivered this morning (they're half expecting something to be missing/incorrect from the radiator list, which seems to be a fairly standard occurrence, but no indication of this as yet, and clearly something they're used to). I'm currently staring at a monster of a K3 that's going in the kitchen/dining area, and have watched them carry through radiators to go into the upstairs rooms.
So far so good (touch wood!) First impressions only, but I've gained a huge amount of reassurance already from having seen the guys go about their work, and from the interactions I've had with them while trying to keep out of their way.
- 26 Forums
- 2,221 Topics
- 49.3 K Posts
- 179 Online
- 5,881 Members
Join Us!
Podcast Picks
Latest Posts
-
RE: Should Our Water Circulation Pump Be Configured to Run All The Time?
ive got a similar issue with my Vaillant. when it was o...
By AdamK , 5 minutes ago
-
RE: Twin 10kw Grant Aerona Volumiser Tanks using lots of power
@adam Hi just jumped on this thread as I too have 2 10k...
By bretix , 1 hour ago
-
RE: Help me keep the faith with my air source heat pump installation
on a facebook thread someone has comented to the effect...
By AdamK , 1 hour ago
-
The timing of training and inference are very applicati...
By wully , 3 hours ago
-
RE: Samsung Heat Pump – Can't Activate TW2 Pipe Sensor (for Delta T Control)
Wanted to add an update. As I am running HomeAssistan...
By bubuontheweb , 4 hours ago
-
RE: Grant 13kW Aerona3 - issues getting zones to temp
You are correct you dont need the second pump if there ...
By JamesPa , 4 hours ago
-
RE: New Fogstar 15.5kWh upright solution
From my experience with inverters from different Far Ea...
By Transparent , 5 hours ago
-
@bontwoody Thank goodness you are ‘back on-line’ so to ...
By Toodles , 6 hours ago
-
RE: Automation options to maximuse efficiency & ToU tariffs
@majordennisbloodnok Seems reasonable. It would be m...
By Batpred , 6 hours ago
-
RE: Havenwise App Help & Forum Support – Get the Most from Your Heat Pump
@hcas OK Thanks. Will do.
By bontwoody , 9 hours ago
-
RE: What crazy nonsense are inverter limits and why are they imposed?
@transparent Thank you for a very comprehensive, tim...
By Batpred , 11 hours ago
-
RE: Isolating the system for a planned power cut
@transparent 😊 I may have lost you there.. I ...
By Batpred , 12 hours ago
-
RE: How good is the app support for your heat pump?
We have a Grant Aerona 290 15.5kW heat pump with their ...
By GrahamF , 13 hours ago
-
-
RE: Low COP and unevenly heated rooms with 12kW Samsung AE120MXTPEH / AE260TNWTEH
Where is the noise coming from. If its the pump then p...
By JamesPa , 16 hours ago
-
The Mars and Richard Kitchen Show
Just stopping by to say: 1) Mars I'm so sorry that yo...
By Lucia , 1 day ago
-
RE: Electricity price predictions
Without getting too much into politics, given that the ...
By Batpred , 2 days ago
-
UK Consumer Law Reality Check (for anyone dealing with ...
By DREI , 2 days ago
-
@dgclimatecontrol Thanks... this was resolved back in M...
By Sandman1600 , 2 days ago
-
Electrical is the only way forward.. But until we get...
By Batpred , 2 days ago