Opinions please on me putting a 2.5kW roof mounted turbine on my garage - am I mad?
Hi folks. I have ASHP, Solar PV (5.46kW) and a 10kW battery set up. I’m thinking of putting a 2.5kW roof mounted turbine on my garage.
the garage houses the PV, Battery and Inverter already.
wind speed per second for my location is an average of 6.
my thinking is that it would be beneficial for an outlay of circa £3k because although 2.5kW isn’t huge it at least still produces at night and certainly through the winter months.
I’m thinking this could significantly offset the cost of running the ASHP and would make its money back in about 6 years.
I would put it on the back end of here.
Am I deluded?
I don’t think you’re mad. If you can afford it, and you have a property where you can add a wind turbine, that alone usually trumps an immediate RoI. I’d like to know more about the turbine you’re thinking of putting in.
@transparent knows a thing or two about turbines.
Pre-order: The Ultimate Guide to Heat Pumps
Subscribe and follow our Homeowners’ Q&A heat pump podcast
@editor I’m researching models at the moment Mars, it’s not easy or obvious so far.
in terms of the cost, ScotGov offer a £2500 interest free loan, but no grants at the moment.
im thinking for £20 per month over 10 years it merits serious consideration. The price of a mobile sim contract really.
I don't know about the rules in Scotland, but I think that planning permission would be required since you also have a heat pump.
Posted by: @marvinator80I’m researching models at the moment Mars, it’s not easy or obvious so far.
Yeah, I know. It’s not a massive market so really interested to see what you discover.
Pre-order: The Ultimate Guide to Heat Pumps
Subscribe and follow our Homeowners’ Q&A heat pump podcast
@derek-m I’ve seen that quoted but I think it might be a widely circulated error. Will check with planning though if I can find a model to move forward with.
Posted by: @marvinator80I’ve seen that quoted but I think it might be a widely circulated error.
If you check permitted development rules for Scotland you can ASHP x1 and a Micro Wind Turbine on a site without planning.
6.21 This provides potential opportunities for one MWT and one ASHP within the same curtilage, but not more than one of each using permitted development rights. For example, this would allow for a wind turbine to provide the electricity to power a heat pump.
When looking at turbines make sure you take in to account
Different outputs at different wind speeds not just the average.
Building effect on output - which be very dramatic unless many metres above the building, due to turbulence
Posted by: @AnonymousPosted by: @marvinator80I’ve seen that quoted but I think it might be a widely circulated error.
If you check permitted development rules for Scotland you can ASHP x1 or Wind Turbine on a site without planning. If you want both it is no longer permitted development.
When looking at turbines make sure you take in to account
Different outputs at different wind speeds not just the average.
Building effect on output - which be very dramatic unless many metres above the building, due to turbulence
yeah, I will definitely talk to planning if I can find a viable system.
why do you think they restrict it in that way. How does having a ASHP make them require planning for a small roof mounted turbine?
This may be of interest:
Is It Worth Adding a Wind Turbine to Your Home Solar Installation?
Interesting notion @marvinator80
In case you were wondering, here's how I would apply a mechanical lever to the wall of your garage in order to shake the bricks apart:
Better still, I could achieve the damage much faster if I used a varying force at the top of the pole.
Instead of it always being applied in the same direction, I would vibrate it randomly around the horizontal plane.
At some point in time it might even achieve resonance with the length of the pole above the upper bracket, which would amplify my efforts.
The foregoing explanation is based on a true story...
... which happened so often that the major UK company who developed 1kW wall-mounted wind-turbine lost their sales deal with B&Q.
Alternatively you could use a ground-mount tower.
Here's one I built using a triangular aluminium lighting truss which was being offered by the liquidator of a night-club that had closed down.
The horizontal pole close to the bottom is called the jack-stay.
You attach a rope to that in order to raise and lower the tower around the bearings at the base.
Some people then remove the jack-stay.
I decided to leave mine in place, which adds to the rigidity of the mechanism.
Save energy... recycle electrons!
- 26 Forums
- 2,131 Topics
- 46.8 K Posts
- 17 Online
- 5,656 Members
Podcast Picks
Latest Posts
-
RE: Say hello and introduce yourself
Welcome to the forum, please feel free to ask any quest...
By JamesPa , 18 minutes ago
-
RE: Heat Pump Servicing & Maintenance – Good Value or Rip-Off?
@heat-pump-newbie Yes you need F Gas engineers like us ...
By dgclimatecontrol , 2 hours ago
-
RE: New Vaillant aroTherm Plus in black - When will it come to the UK?
@editor I know it was formally announced at Ish the oth...
By PatrickVito , 7 hours ago
-
@moman0311 welcome to the forums. I've received your em...
By Mars , 8 hours ago
-
RE: Anyone still weathering it out with Agile?
Yes, but now try finding a working phone box….
By Majordennisbloodnok , 24 hours ago
-
RE: Thermostat for Ideal Logic Air with 3 zone support
No harm at all in plumbing it as 3 zones, I would have ...
By JamesPa , 1 day ago
-
RE: ASHP heat output monitoring
@carlo I see there is a discussion in Facebook user gro...
By Tim441 , 1 day ago
-
RE: Flexi-Orb Heat Pump Scheme: A Game-Changer for the UK's Heat Pump Industry
MCS have set a potential trap in the new version of MCS...
By JamesPa , 2 days ago
-
RE: Who has a V2G EV installation
General comment on battery care... I guess if ev is on ...
By Tim441 , 3 days ago
-
@old_scientist like for like comparisons are almost imp...
By Tim441 , 3 days ago
-
RE: Who's your electricity provider and what's your tariff?
@old_scientist There is an option in the Tesla app that...
By Toodles , 3 days ago
-
RE: Mitsu Wireless Controller and MelCloud
On the FTC5 I think this requires the dip switch on the...
By Abernyte , 3 days ago
-
RE: Octopus Cosy & Octopus EV + bidirectional smart tariff, together. What, eh?
@old_scientist me too. Just installed my new heat pump ...
By Eliuccio , 5 days ago
-
RE: Is your heat pump insured?
Yup just spoke to Privilege to inform them of my impend...
By Scalextrix , 5 days ago
-
RE: Forum updates, announcements & issues
Just to keep everyone in the loop, as the site continue...
By Mars , 5 days ago
-
RE: Fast DHW setting on Midea (Clivet) heat pump
@simon-w, is this something you could potentially assis...
By Mars , 6 days ago
-
RE: Share Your Experiences with Heat Pump Manufacturer Support
Fwiw I called my installer out for the first time a few...
By JamesPa , 6 days ago
-
RE: Long term efficiency degradation
@jamespa yes as I thought thanks. We have a reaso...
By Scalextrix , 6 days ago
-
RE: Sunamp Thermino Heat Battery
@jamespa A few days after the installation had been com...
By Toodles , 1 week ago
-
RE: Planning Permission May 2025
Fair enough. I have read the legislation and MCS020a ...
By JamesPa , 1 week ago