@transparent they are all in parallel. I only did the sets of 4 to decrease the total time to get them all up. In parallel I can only get 36w into them at a time. With 4S @ 14V I can get 4x the power into each cell Vs via 16. So I did a rough and dirty with the sets of 4S and then a final with 16P @ 3.6V
I read that the final bit of charge to top balance is best added when the cells are under compression (e.g. within the Seplos box but not hooked up to the BMS) as to prevent any unfortunate swelling; any thoughts?
@korwraith I would not be able to do that as my charger doesn't go high enough. Makes sense to me though
Posted by: @bataltoI would not be able to do that as my charger doesn't go high enough...
Put it on a shelf, perhaps?
Apologies, it's Friday.
I'll stop making puns, and instead make another batch of marmalade.
There's not many Seville oranges around this year.
Fortunately I bought 10Kg in a local greengrocers.
Save energy... recycle electrons!
Save energy... recycle electrons!
Just wondering what Hybrid inverters you guys are using with the LV battery kits? I'm struggling to find a 3 phase one that will talk to this kit. Any suggestions?
That question is more complex than it first appears @mookyfoo
Let's start with what I hope is the most positive direction in which you could proceed:
I've been running a Growatt SPF5000ES for the past year. The trial is now being expanded to encompass multiple units, initially still to be operated from a single-phase grid supply.
The photo shows "work in progress". The wall-space currently occupied by the grid-tied Growatt MIN 3600TL will later be relinquished in favour of another hybrid off-grid inverter.
A multi-inverter installation requires connecting data and balancing wires between the units.
They must share a single battery-bank, but this can be segregated into two or more physical batteries, each with its own BMS.
The SPF5000ES can also be wired to support 3-phase operation using a minimum of three inverters. (Split phase use is not supported).
Here's a wiring diagram from page-28 of the User Manual
The wiring diagrams are not 100% accurate, sometimes showing link-wires connected to ports which are actually the wrong way around.
However, the data cables do at least have male and female ends, which makes it 'impossible' to get these wrong!
The User Manual is less clear on the way in which the inverter's parameters must be configured.
Once the command is given for them to operate as a set, they are powered down and then re-started.
At that point one unit powers up as the Master, and replicates its settings to the others.
Since you can't define which is to be the Master unit, I assume that all the other parameters must be manually configured before this re-power sequence.
If not, then a 'wrong' parameter which happens to be on the unit which declares itself as 'Master' will thence be sent to the Slaves.
Beware too that some parameters will apply to each inverter in the set, whilst others might be divided across the number of inverters that you've installed.
Eg, specifying the battery charge current at 70A, means that each inverter will contribute that amount.
It's all to easy to exceed the maximum specification for your LiFePO4 cells.
Think about a 3-phase installation with uneven numbers of inverters across the phases, and you'll begin to realise the difficulties in knowing which parameters do what!
Finally, yes I'm pretty sure that there are other (Chinese made) off-grid hybrid inverters which could be used similarly.
But I'm having great difficulty in discovering which these are.
I spent a while looking into those made by Shenzhen Next Power Technology which have a similar specification to Growatt's SPF5000ES
However I discovered that at present the Next hybrid-inverters
- don't have any firmware or interface for parallel operation (even on single-phase)
- do not meet CE & or UK safety requirements for their 240v AC connections
This situation may change. After all, Growatt bought in that parallel capability, which is why it's implemented via a separate module.
So, why do I think that there are other hybrid inverters with 3-phase capability?
Because they're used inside other large off-grid stand-by battery units being sold (at a hefty price) for use as emergency supplies.
Save energy... recycle electrons!
@transparent Thanks for that post. I wasnt aware you could share one battery across 3 inverters which could be useful. I have seen 3ph hybrid inverters available which presumably makes installation bit easier than 3 separate inverters, but they arent of a brand that is listed as supported by the Selpos kit. It just seems like there isnt enough standardisation across the manufacturers if there were you could just pick and chose what to use which would make life easier.
@mookyfoo - there isn't even enough consistency within Growatt, let along hoping for standardisation across manufacturers.
There's a high proportion of inverters which are actually made by a single manufacturer, but then loaded with different firmware and rebadged.
For example, this model manufactured by Next Technology in Shenzhen
can be found advertised on Amazon UK under three different brand names.
None of the three have modifications to add approved cable-clamps for the 240v connections, and none state what firmware variants they may or may not have.
In this particular case, the enclosure is distinctive, and the model is traceable back to Next Technology.
But most other instances of rebadged inverters, there are variations which are sufficiently different that it isn't possible to identify the original manufacturer with any great certainty.
That creates difficulties when trying to assess whether a particular model is suitable for linking in a 3-phase installation.
Since off-grid inverters contain their own 50Hz clocks, it is extremely important that they maintain 120 degrees phase difference when generating from stored energy in the battery.
A software error or thermal protection fault could too easily take one inverter off the system, resulting in possible damage to 3-phase load-devices such as a heat pump.
Only the original manufacturer will be able to know the features within the firmware of the various models they produce, and how they fail safe under fault conditions.
Returning to the Growatt SPF5000ES hybrid off-grid inverters, I will be testing these under external software controls for several months before even considering the move to a 3-phase configuration.
There are just too many ways in which one inverter within the inter-linked set might fail to implement a legitimate command.
At this moment, Growatt themselves do not specify which commands need only be sent to the Master unit in the set, and which must be sent separately.
The situation is complicated further once you consider the range of fault/alert codes which any one inverter might throw up.
These aren't initiated by software under my command, and yet must be handled appropriately.
On the matter of using a single storage battery for 3-phase off-grid use, I can't see how it would be safe to consider using separate batteries for linked inverters.
If each inverter in the set was drawing power from a different battery, then the thresholds for sensing State of Charge (SoC), High-volt overcharge, and Low-volt discharge will slightly differ.
That would simply add to the complexity of fault-handling across the inverters generating the 3 phases.
Please do continue to look for other hybrid off-grid inverters which might be suitable for use with the Seplos Mason box, or similar.
We can then discuss here whether the design contains the necessary protections and fail-safe firmware.
Save energy... recycle electrons!
I know they are furiously expensive and enormous, but I’ve been running on Outback products exclusively since 2007 without a single issue.
utterly reliable kit.
Off grid on the isle of purbeck
2.4kW solar, 15kWh Seplos Mason, Outback power systems 3kW inverter/charger, solid fuel heating with air/air for shoulder months, 10 acres of heathland/woods.
My wife’s house: 1946 3 bed end of terrace in Somerset, ASHP with rads + UFH, triple glazed, retrofit IWI in troublesome rooms, small rear extension.
- 22 Forums
- 2,058 Topics
- 44.9 K Posts
- 31 Online
- 3,308 Members
Join Us!
Trusted Installers
Struggling to find a reliable heat pump installer? A poor installation can lead to inefficiencies and high running costs. We now connect homeowners with top-rated installers who deliver quality work and excellent service.
✅ Verified, trusted & experienced installers
✅ Nationwide coverage expanding
✅ Special offers available
Latest Posts
-
RE: Planning Update: 1 Metre Boundary Rule for Heat Pumps Has Been Scrapped
This is indeed welcome news. In addition the new legi...
By JamesPa , 6 hours ago
-
RE: Heat Pump Manufacturers Recommending Buffer Tanks
On our original boiler install, I did have a 140L buffe...
By Johnmo , 14 hours ago
-
RE: Is your heat pump insured?
@benson fairly typical of some insurers.
By KevinPotts , 17 hours ago
-
RE: Getting the best out of a heat pump - is Homely a possible answer?
@majordennisbloodnok I am wearing a glazed expression n...
By Toodles , 17 hours ago
-
RE: Rate the quality of your heat pump design and installation
Yes the HP is running weather compensation and I’ve lef...
By Davesoa , 24 hours ago
-
RE: IVT Greenline high pressure switch and electrical cassette errors
OK, so when the HP comes on it becomes obvious.It's on ...
By tdudgeon , 2 days ago
-
RE: Is Your 6kW Air Source Heat Pump Really a 6kW?
@johnmo I think we’ve been trudging through the same...
By SUNandAIR , 2 days ago
-
RE: How To Balance Radiators & the Role of the Lockshield Valve: A Homeowner's Guide
Good luck, I hope it all works out!
By JamesPa , 3 days ago
-
@johnd it's a difficult one, because we've seen instanc...
By Mars , 3 days ago
-
Win a 6-panel PV courtesy of egg and Renewable Heating Hub
Our epic giveaway just went live! Want to win a 6-pan...
By Mars , 3 days ago
-
RE: Yes, the "zoning with ASHP" topic again...
James, thanks again for your thoughtful and persistent ...
By HarryRea , 3 days ago
-
RE: Is this normal? Click of the DHW returning to space heating
So the Lone Ranger returned today! Even though we thoro...
By Grantmethestrength , 3 days ago
-
RE: Vaillant & OVO partner up to offer Heat Pump Plus
Hopefully iv done the right thing today by signing up t...
By Westkent , 4 days ago
-
RE: Battery sizing - How low can you go!
My own experience with connecting four batteries to thr...
By Transparent , 4 days ago
-
RE: Plate heat exchanger considerations
Work on 2-3 percent per degree. This is a reasonable e...
By JamesPa , 4 days ago
-
RE: Advice for ground source heat pump in new build with PV and batteries
The useful bit is the bit that specifies the heat loss ...
By JamesPa , 4 days ago
-
RE: Volumisers in Heat Pump Systems: Does Placement Matter?
You’re absolutely right that during defrost the refrige...
By Mars , 4 days ago
-
@editor thanks Mars that’s the same table I found in th...
By Gary , 5 days ago
-
RE: Tariff and charging strategy advice please
They haven't asked me to prove that I have an EV (I do)...
By JamesPa , 5 days ago