Indra V2H Trial
Indra V2H Trial in case it hasn't been posted before
The Indra/Kaluza V2G Trial 3 years ago was constrained by DNO's not approving the chosen sites for the full export rate. I think this was 7kW (32A), but perhaps @jeff can confirm that.
The Mk I V2G charger had only one setting for import/export. So if the DNO agreed maximum export of only 20A, then the charging rate for the Nissan Leaf was similarly limited.
Indra have now taken the sensible step to feed stored-charge only to the home, with none being fed back to the grid. This is usually done by placing a current clamp on the live feed between the smart meter and the consumer unit. The charger then calculates how much current to supply from the car battery.
Once the Electrical Networks Association (ENA) test and accept such an export-limitation system, the DNOs will 'trust' it, allowing the Indra V2H chargers to be installed under the two relevant approvals:
- G99/G100 for grid export (still required although the export is set to zero)
- Low Carbon Technology (LCT) consent for grid-connected devices; which currently encompasses EV-chargers and Heat-pumps
Save energy... recycle electrons!
The electric spec of the v2h and v2g indra chargers appear to have the same limits unless indra have a cut/paste issue with their website.
And the 6KW tallies with the post from @robl about the ovo trial chargers themselves even though @robl was then limited to 4KW
@jeff I'm pretty sure they are the same unit! We are still on the Ovo V2G trial, it finishes in a few weeks. The original installation involved a current clamp on the main Live tail, which is used to ensure that we never export more than 16A (we have PV as well, so without this clamp it could easily exceed 16A). The current clamp is a standard fit for the V2G trial.
They really should have fitted standard elec meters for import and export, as all of the embedded ones are acknowledged to be low accuracy and I don't think they measure some of the parasitic losses annoyingly. Meters are cheap, at least compared to the Ovo trial (I think surprisingly expensive, as the hardware is made in low volume, and the install took some time).
I intend to ask Indra to flash the unit to V2G in a while - which I think they will do for free - I expect that they get in-use data from it. The V2G trial has a fixed export tariff, which worked well in the past - but as elec prices skyrocket it makes less sense as it's not actually linked to the fixed import rate. So at the moment Ovo (well a subsiduary of) tell the car when to charge and discharge, and we make a profit as our export rate is higher than our import. They pay us for excess PV too as they cannot differentiate between car and PV export, so we may well still make a profit - but there is no incentive to actually plug the car in anymore except to charge it!
In contrast, V2G and Octopus Go make a lot of sense, as there is a huge price discrepancy again overnight to daytime. I am also more comfortable with Octopus/another variable tariff, as I have always considered the financial aspect of the trial to be "too good to be true", and so not representative.
I think most people with batteries or V2G head over to Octopus.
Thanks for that info @robl If your Indra V2G charger was limited to 16A export by the DNO (ie the usual limit for grid-export) then did that 3.68kW also apply to charging the Leaf?
I believe the upper limit is defined by the 'charger module' which Indra use internally. I've now checked and I think it's 6.5kW, not 7.5kW as I suggested above. The module is made by the Dutch company, PRE Power Developers... a reputable company in this field.
Posted by: @roblI intend to ask Indra to flash the unit to V2G in a while
Did you mean to write flash the unit to V2H in a while?
Posted by: @roblThey really should have fitted standard elec meters for import and export
Could you elaborate on this please?
What are you looking for which couldn't be measured by your Smart Meter?
Although OVO/Kaluza are undertaking these trials using participants on a fixed tariff, that's only because they haven't yet been able to offer a ToU tariff like Octopus' Agile/Go.
Once customers are using ToU, the only way to obtain correct billing is for OVO's software to read the Smart Meter registers. You can't have separate import/export meters because they would have no concept of when the half-hour price-periods begin and end.
Save energy... recycle electrons!
Yes, flash to V2H.
The reason to add extra meters would be to evaluate the round trip inverter-car-inverter performance. There is no way to do that as standard, although you’re right, from a billing perspective they are doing a plausible thing given no tou tariff. It is in fact quite lossy- roughly 2kWh of loss / day before inverter efficiency is taken into account. There is also a lot of reactive power, 4A so 1kVA if I remember correctly when the unit is active but not charging/discharging.
I think most of the loss is due to the chademo cable hookup - being dc it requires locking in place, and several big contactors always energised.
I would love to see the J1772 ac socket standard protocol upgraded to bidirectional - that really would get mass adoption of V2X going.
Interesting discussion here. I am personally looking forward to the V2H trial, and Indra aren't very forthcoming with info/availability (clearly its a commercially sensitive matter).
The most important thing for my use case is to have a mini-grid (i.e. backup during grid outage), which the wallbox unit doesn't do at this point, nor does it have V2H capability yet but its "coming".
Having checked out PRE power developers on the Type Test register, they are indeed able to do G99 (>3.68), but not yet G98 (up to 3.68) or G100 (export limiting, for examples like noted above where other existing generation tech may "overload" the grid (hate this word in the context, as its typically a voltage issue, rather than a current/thermal issue).
Any V2H solution will normally follow the G100/1 process for both import and export, and as G100-2 is published this will be even more valid after its introduction period (though one might prefer to opt for G100/2 due to the increased voltage margin/range available under it).
I would not have thought DNO's would require a limitation to the IMPORT for charging the vehicle, though there may be cases where the demand of the house may exceed the DNO fuse rating - in these cases you can either request that the DNO upgrades the fuse to 100Amps (typically free of any works) or you have to pay for specific import restriction device such as those implemented on the OVO and other trials, that monitor the power flows to ensure safe limits (whether that be at 100amps or below for that matter if a fuse upgrade is not possible/too costly).
The way forward is to have an all-encompassing solution such as from Indra, which will hopefully limit import (if needed), limit export(smart for high average demand/high peak use cases), and provide mini-grid for backup power.
Would be keen to hear from anyone if they know more about the Indra V2H trial details/dates/costs, as buying a car for that purpose is quite a move in the dark just now (although we really want to do so anyway even if we have to settle for a V2g charger for some years)
Hi @robl, did you ever get your unit converted to V2H, or has anyone else had this done? I also have a unit from the Ovo V2G trial and would love to get it to just cover some of the load on the house. I have got some battery storage also, not sure if that would complicate things? Perhaps you'd have an idea @transparent?
Cheers
Update: Managed to join the trial even though the application date had passed..
Thank you for your email and interest in our V2H Trial.
We have added your details to a list and will be in touch shortly with next steps.
Yes, we are offering existing V2G customers the opportunity to upgrade their units to a V2H unit.
I hope this helps.
We did get on the V2H ‘trial’. I use quotes, as I think the trial was for new entrants; we had the indra box already. The process was:
Change provider to Octopus energy.
ask indra by email
Forward on to Indra an email from Ovo, confirming I owned the indra box.
The above took 2 days. Quick! Then the slow bit… there was something wrong with the way our smart meter was setup - Ovo used to be able to read it, but octopus couldn’t. They could read the gas(which is via elec) but not the elec. Over 3 months many emails back and forth, lots of photos, etc. A friend offered a bizarre solution: tweet @Octopus…. Within a day I joined twitter…got a reply, a tech guy could see something wrong, they fixed it, It worked! Weird world.
Hi @robl, thanks for the info. I too recently moved from ovo to octopus, I have probably the same issue, meter not being picked up by octopus, I left my gas meter with ovo as gas was still cheaper. Don’t suppose you have contact details for the octopus engineer, they seem stuck and I really want to get onto the Go tariff to save some money
@robl Thanks for the info you provided on the other thread, the graph of the v2h unit reacting to a resistive load was helpful. Just going through the steps with Indra.
Quick question - Is there a minimum load that the v2h unit needs before it reacts? I think the wall box unit requires a min of 1.2kw.
Thanks for the info.
- 21 Forums
- 1,962 Topics
- 42.6 K Posts
- 67 Online
- 2,276 Members
Join Us!
Heat Pump Dramas?
Thinking about installing a heat pump but unsure where to start? Already have one but it’s not performing as expected? Or are you locked in a frustrating dispute with an installer or manufacturer? We’re here to help.
✅ Pre-Installation Planning
✅ Post-Installation Troubleshooting
✅ Performance Optimisation
✅ Complaint Support (Manufacturer & Installer)
Latest Posts
-
@eliuccio Unfortunately, whilst I agree with a lot of...
By JamesPa , 5 minutes ago
-
RE: Volumisers in Heat Pump Systems: Does Placement Matter?
@jamespa the key point, from my own logical thought pro...
By Mars , 10 minutes ago
-
RE: Newbie out of her depth – Samsung AE120RXYDEG 12kW heat pump
@bami I think if the heat loss documentation matches a ...
By bontwoody , 27 minutes ago
-
RE: What is the best strategy for operating a very oversized heat pump?
@jamespa I'm afraid that's over my head but if anyon...
By IRMartini , 55 minutes ago
-
RE: Setback savings - fact or fiction?
And here in case any one wants it is the code I used in...
By cathodeRay , 1 hour ago
-
RE: Samsung Gen 7 R290 12kW is not behaving how I expected
Definitely its in the 20xx FSVs. Conversely it may be...
By JamesPa , 1 hour ago
-
RE: Towel rails. An unexpected final hurdle
We have both Normal Rad for heating the room and then a...
By IRMartini , 3 hours ago
-
RE: Heat Pump Sizing & Installation Costs
Perhaps useful to have installed date too? To get conte...
By Tim441 , 5 hours ago
-
RE: SolarPV tables / online calculator
I'd be interested what others find whilst using that we...
By Majordennisbloodnok , 7 hours ago
-
RE: F.788 Building circuit pump reports internal fault - Vaillant Arotherm
Guess I have to wait for engineer visit. I really hope ...
By jeegnesh , 19 hours ago
-
RE: Act now to defer the UK road tax increase on EVs
@majordennisbloodnok Damn right sir. my attempt at iron...
By Jancold , 22 hours ago
-
RE: ASHP and heating issues in new build house
That’s good gives you more capacity. It made me think, ...
By Terry1812 , 23 hours ago
-
RE: Seewet manhole cover within r290 exclusion zone
Thanks! I asked Vaillant, and they say I should be fi...
By dbrb2 , 1 day ago
-
Looking for the Grant Aerona 3 setting to turn off completely at 20 OAT
I'm running my Aerona 3 on WC and the 'warm end of that...
By damonc , 1 day ago
-
RE: Do I just go with the lowest quote for my heat pump?
So after signing in Sept in two weeks the install may s...
By Jancold , 1 day ago
-
RE: Victorian Semi Retrofit / Extension ASHP and UFH Advice
When you are renovating is always a good time, as it ma...
By JamesPa , 1 day ago
-
RE: Just one room not reaching desired temperature
Looks like this issue is now resolved. Aira installed a...
By ChandyKris , 1 day ago
-
There have been several people on the OpenEnergyMonitor...
By RobS , 2 days ago
-
RE: Say hello and introduce yourself
Good point @jamespa But that probably strengthens @ch...
By Transparent , 2 days ago
Latest Topics
-
Heat Pump Sizing & Installation Costs
By Mars 7 hours ago
-
Volumisers in Heat Pump Systems: Does Placement Matter?
By Mars 8 hours ago
-
SolarPV tables / online calculator
By MichelleC 15 hours ago
-
By Toodles 2 days ago